ETL+ Load Replace Examples
Examples of source data and the target tables that result from a Load Replace.
Example 1
Extract, Transform and Load (ETL) page
The seq
column represents a sequentially incremented value.
Design page. No PK (primary key) in target table.
Â
Source
Target Table Before
Empty
Target Table After
Log: (4 rows loaded)
2nd Load Replace
Â
Log: (1 rows replaced)
3rd Load Replace
Â
Â
1 = pre-existing row,
not changed
2 = new row
3 = replaced
Log: (2 rows replaced)
The Target Table has two rows with a row
column = 2.
If the row
column had been configured as a DW PK (primary key) on the Design page then the relational database referential integrity rule would have updated the existing row instead of adding a new row.